Error KI 249 upon PR creation pointing into Profitability Segment

Paulo_Vitoriano
Active Contributor
0 Kudos

Dear Colleagues,

I get an error KI 249 during PR creation and it seems like the reason for the error is a WBS and a Profitability Segment assignment at the same time. While I do assign WBS manually, it is not clear how the Profitability Segment gets assigned and how can I see it from the PR before saving the data. It is an account based PA in S/4HANA, and the project profile behind the WBS is not part of COPA derivation settings, which confuses even more.

Thank you,

Paulo

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Paulo,

In your PR, are you using account assignment WBS/Project and GL combination? If that is the case then check in OKB9 if GL is assigned to Profitability Segment transfer.

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Abhishek,

No, OKB9 would be too simple, it is not based on the GL account. It is based on the material master record that is triggering a COPA account assignment in my case.

Thank you,

Paulo