Error KI 249 upon PR creation pointing into Profitability Segment

Dear Colleagues,

I get an error KI 249 during PR creation and it seems like the reason for the error is a WBS and a Profitability Segment assignment at the same time. While I do assign WBS manually, it is not clear how the Profitability Segment gets assigned and how can I see it from the PR before saving the data. It is an account based PA in S/4HANA, and the project profile behind the WBS is not part of COPA derivation settings, which confuses even more.

Thank you,

Paulo

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Oct 28, 2019 at 07:28 AM

    Hi Paulo,

    In your PR, are you using account assignment WBS/Project and GL combination? If that is the case then check in OKB9 if GL is assigned to Profitability Segment transfer.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.