Forecast split into weeks has problem

0 Kudos

Forecast is loaded in months. When choosing weekly bucket to display in the planning book, for some products, forecast is correctly distributed equally in all 4 weeks. But for some products, whole monthly forecast is put into one (last) weekly bucket for that month. I do not know why this is happening. Since this is for some products, I assume it is due to some master data setting. What fields should I verify? Or in general also what configs or settings should I check and now, in order to solve this?

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please check following points

Does location has a shipping calendar which uses a factory calendar with non-working days ?

Have you used /SAPAPO/SDP_RELDATA BAdI ?

Check transaction /sapapo/sdp_split to define period split profile.

Also check product master SNP2 tab for Forecast Horizon and Period Split.

Best Regards,

R.Brahmankar