Forecast is loaded in months. When choosing weekly bucket to display in the planning book, for some products, forecast is correctly distributed equally in all 4 weeks. But for some products, whole monthly forecast is put into one (last) weekly bucket for that month. I do not know why this is happening. Since this is for some products, I assume it is due to some master data setting. What fields should I verify? Or in general also what configs or settings should I check and now, in order to solve this?
Hello,
Please check following points
Does location has a shipping calendar which uses a factory calendar with non-working days ?
Have you used /SAPAPO/SDP_RELDATA BAdI ?
Check transaction /sapapo/sdp_split to define period split profile.
Also check product master SNP2 tab for Forecast Horizon and Period Split.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.