How to mass update Subcontract PO components?

Dear experts,

When the BOM of a semi-finished product changed, the business department have to update components of

the Subcontract PO by ME22N at item level.

Is there any t-code or standard program can be used to mass update Subcontract PO components for several POs at the same time?

Thanks so much.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Oct 18, 2019 at 09:40 AM

    Hello,

    Currently in standard SAP there is no functionality to update/re-explode Subcontracting PO components after BOM changes.

    You can use LSMW or BAPI using BAPI_PO_CHANGE to re-explode the BOM.

    Also refer SAP KBA 2736604 - BOM not re-explodes for all schedule lines in purchase order (PO)

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.