Release strategy is re-triggered when work order TECO is reversed

We are experiencing the following scenario:

1. Work Order is created with a PR

2. PR is fully released and converted to a PO

3. Work Order is set to TECO

4. TECO is reversed on the work order

5. PR release strategy is re-triggered

We are using header releases for PR's. How do we prevent the release strategy from re-triggering?

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Oct 18, 2019 at 07:08 AM
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 17, 2019 at 07:18 PM

    Hi Judd,

    Please check if you have any enhancements in your system, maybe as a part of VIM.

    To my knowledge the cancelation of TECO should not impact existing POs in the standard system, unless you change quantity or anything outside tolerance, that anyway must be an enhancement.

    Regards,

    Paulo

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.