Skip to Content

How to Close the Initial C4C Project?

Hello All,

In my project we have completed all the activities, But status of the First Implementation project stays Tested.

So I have a question on how do we close the project ?

Attaching the screenshot for the same. status.png

status.png (39.6 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Oct 25, 2019 at 10:30 AM

    Hello Harsh,

    I guess you are trying to close the project in Test System. You cannot close the project in test system. Check the KBA

    https://apps.support.sap.com/sap/support/knowledge/public/en/2194540

    Regards,
    Bharathraj

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 16, 2019 at 07:28 AM

    Hi Harsh,

    from your last comment I assume you are trying to close First implementation project in Test tenant and that is not possible. It is possible only in Production tenant, because closing The Go-Live activity (which is also not present in Test tenant) is prerequisite for Close activity.


    Final status for First implementation project in the Test tenant is "Tested".

    For more information visit: https://www.anodius.com/en/qa/close-initial-c4c-project/

    Regards
    Dominik Filip
    Anodius

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 16, 2019 at 12:36 AM

    Hi Harsh,

    1. Go to Business Configuration work center
    2. Select Implementation Projects view
    3. Highlight the First Implementation project and choose Open Activity List
    4. Select the Go-Live tab
    5. The activities Close Project and Confirm Go Live are Completed

    Br,

    Keshav

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Keshav,

      Thanks for the response. Though I only see these 3 activities on the Go Live tab in the activities which are closed.

      1. Assign Contact to Contact Type

      2. Validation of IT Contacts

      3. Disable Data Migration per Object

      I don't see an option to close the project.

      Thanks

      Harsh Shah

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.