Goods receipts/goods issue

0 Kudos

Hi Experts,

Goods Receipt of a work order is blocked when goods issue is not completed for all componenets of the work order BOM

Problem :

If there are backflush components on the operation which triggers auto GR,then with confirmation of the operation system wants to do Gi and Gr at the same time . The GR is blocked due to open GI and then we get an error message when doing the confirmation of operation and as well as we get a COGI entry for movement 101

Accepted Solutions (0)

Answers (2)

Answers (2)

Caetano
Product and Topic Expert
Product and Topic Expert

Hello

This is not possible in standard. The following blog proposes a solution using an enhancement:

https://blogs.sap.com/2014/01/21/without-gi-confirmation-and-without-confirmation-gr-is-not-possible...

Regards,
Caetano

0 Kudos

We would like to have an adaption so that GR is done later to avoid this error message and cogi enteries with that we only had COGI entries if GI could really not to be done completly

Is there a possibility to eg.define a time out between GI and auto GR ? So that GI for all backflush material is already done

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

In this case, you should avoid the automatic goods receipt, that is carried out when you use control key PP03, and you should post the goods receipt manually later, in transaction MIGO for example. Please observe that there will be no standard check to ensure that all the components were issued and you need to have a custom logic implemented if you want to have this check.
Regards,
Caetano