Hi Experts,
Goods Receipt of a work order is blocked when goods issue is not completed for all componenets of the work order BOM
Problem :
If there are backflush components on the operation which triggers auto GR,then with confirmation of the operation system wants to do Gi and Gr at the same time . The GR is blocked due to open GI and then we get an error message when doing the confirmation of operation and as well as we get a COGI entry for movement 101
Hello
This is not possible in standard. The following blog proposes a solution using an enhancement:
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We would like to have an adaption so that GR is done later to avoid this error message and cogi enteries with that we only had COGI entries if GI could really not to be done completly
Is there a possibility to eg.define a time out between GI and auto GR ? So that GI for all backflush material is already done
Hello
In this case, you should avoid the automatic goods receipt, that is carried out when you use control key PP03, and you should post the goods receipt manually later, in transaction MIGO for example. Please observe that there will be no standard check to ensure that all the components were issued and you need to have a custom logic implemented if you want to have this check.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.