Skip to Content
-1

create a Production Order after requistion as like PR in case of PO

Sir as we raise PR for PO so Is it possible to create any type requisition to create a Production Order as like Purchase order after creating Purchase requisition only?

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Oct 10, 2019 at 10:22 AM

    Hello,

    For production order we have the planned order, we convert planned order to production order.

    Purchase requisation used for purchase order and planned order for production or process order.

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 10, 2019 at 02:37 PM

    Hello Abhishek,

    Generally if you are using MRP

    MRP will do the net calculations and generate the reference proposals like Purchase requisitions for procured items, planned order for the inhouse production materials

    where Purchase requisition will be a reference for the procurement team, to convert PR to PO then proceed for goods receipt

    planned order will be a reference to production team to convert planned order to production order then proceed for confirmation and goods movements

    if you are not using MRP, better to create manual Production order directly

    Regards,

    Venkatesh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.