cancel
Showing results for 
Search instead for 
Did you mean: 

Reconciliation of losses and wastes in subcontracting.

former_member337117
Contributor

SAP Experts,

Query :

I have a query regarding the reconciliation of losses and waste generated from vendor side during subcontracting.

Detailed Explanation :

We follow the standard subcontracting process i.e. create BOM in CS01, -> create PR -> Create Subcon PO -> issue material to subcon vendor through 541 movement type -> Create subcon challan through J1IGSUBCON -> then receive material from subcon vendor through 101 / 543 movement type -> create invoice -> Do reconciliation through J1IGRECON.

Now, as per Indian Govt norms, the govt. also has made it mandatory to file GSTR returns for "losses and waste" in ITC-04 every quarter.

Requried Resolution :

Is there any standard approach to capture and reconcile "losses and waste" during subcontracting in SAP? else, if we need to customize it, what should the approach to capture and reconcile it?

Regards,

Vignesh Bhatt

Accepted Solutions (0)

Answers (1)

Answers (1)

ankurch
Active Contributor

Hi Vignesh,

Please check whether below SAP notes you can use or not -

2689061 - GST India S4HANA: Corrections to subcontracting reconciliation process

2679594- GST India S4HANA: Subcontracting Reconciliation Corrections

Thanks,

former_member337117
Contributor
0 Kudos

Hi Ankur,

I checked the notes, but it doesn't give any clarity about how to capture "losses and wastes" that subcontractor sends against the material and it's process for reconilication.

Regards

Vignesh Bhatt