Dear CO experts,
I'm having an issue with CK11N,
I'm trying to calculate a cost for a composed material ( which has 2 sub meterials ; material.01 and material.02)
in the costing structure, the overheads of the 2 submaterials is of the same value and it's not correct it's actually the sum of the material.01overhead + material.02 overhead.
Can someone plz explain to me why the value of overheads is showing this value instead of the value of each material separtely?
Best reagrds,
Do you have an overhead group assigned to only the sub-materials? One way around this might be to assign the overhead group to the top level material, depending on how you want the sub materials valued of course!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.