I can see the work order estimated cost, would like below clarification?

a) Is there any t code available to calculate estimated overhead, for example KGO2 can be used or not?

b) If there is no standard way then how can I calculate if I know the estimate overhead rate?

c) Can this be updated in Cost tab in account assignment tab of operation or custom field is appropriate?

Thank You!

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Peter Atkin Mar 15, 2017 at 05:19 PM
0

SAP Learner,

There is no standard option for overheads on the Estimated Cost data.

PeteA

Share
10 |10000 characters needed characters left characters exceeded
Preeti Rai Mar 23, 2017 at 11:58 AM
0

In PM work order , below path is responsible for overhead calculation and same can be availanle in costing tab for planned and actual cost in term of overhead.

Plant Maintenance and Customer Service-Maintenance and Service Processing-Maintenance and Service Orders-Functions and Settings for Order Types-Costing Data for Maintenance and Service Orders-Maintain Costing Sheet