Hi,

I can see the work order estimated cost, would like below clarification?

a) Is there any t code available to calculate estimated overhead, for example KGO2 can be used or not?

b) If there is no standard way then how can I calculate if I know the estimate overhead rate?

c) Can this be updated in Cost tab in account assignment tab of operation or custom field is appropriate?

Thank You!

Accepted Solutions (0)

Answers (2)

Answers (2)

preetirai1984
Participant
0 Kudos

In PM work order , below path is responsible for overhead calculation and same can be availanle in costing tab for planned and actual cost in term of overhead.

Plant Maintenance and Customer Service-Maintenance and Service Processing-Maintenance and Service Orders-Functions and Settings for Order Types-Costing Data for Maintenance and Service Orders-Maintain Costing Sheet

peter_atkin
Active Contributor
0 Kudos

SAP Learner,

There is no standard option for overheads on the Estimated Cost data.

PeteA