Account assignment P AND N

can i know when we are using account assignment p and n for particular po

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Sep 25, 2019 at 01:26 PM

    Account Assignment Category - P - Project : It is used when you want to purchase the material/service on WBS level . When GR/Service Entry performed, actual cost hit to the WBS. ( Consumption is done - No Project stock In case of material)

    Account Assignment Category - N - Network It is used when you want to purchase the material/service on Network level or Network Activity level. When GR/Service Entry performed, actual cost hit to the Network or Network activity level.( Consumption is done )

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 25, 2019 at 01:30 PM

    The best way is to check it from customizing in the IMG: Material Management > Purchasing > Account Assignment > Maintain Account Assignment categories.

    In the standard system I believe they are WBS and NWA respectively, so that you would use in PS module, but it can always be changed in any system, so better not to rely on descriptions.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 16, 2019 at 09:59 AM

    Hi,

    When you create any purchasing Request/Order, to which object i.e WBS or NWA should this order needs to get assigned is decided by default from the configuration said above my Paulo.

    Based on Account assigned category WBS in case of "P" or to NWA in cased of "N", user will be able to assign those object to PR/PO.

    Once assignment is made, user (as well as within system) will be able to see commitment cost (once PR/PO are created) and cost actuals (Once Service entry sheet or GRN are made for PO) getting posted against WBS/NWA.

    Hope this helps you.

    Regards,

    Pradeep

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.