on 09-06-2019 8:03 AM
Hi All,
I have created a project and assigned budget to all the WBS Elements and released the budget. for one WBS i have assigned budget of 100000 INR.
Now i am creating a PO in USD with more than the budget value but system is showing no errors. but only with some warnings. i can able to save the PO.
Please let me know how to get error message for budget exceeding.
Regards
Avinash
Hi Shrikant,
The tolerance is defined fine.
Solved it by myself. Actually the issue is with the GL Master data where there is no Tick mark under Control Data tab" Record Account Assignment" which will automatically create Cost element with category "90".gl-account.jpg
Thanks for your reply.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kusam,
Please check the tolerance limit configuration for Budget.
SAP IMG-->PROJECT SYSTEM-->COSTS-->BUDGET---> DEFINE TOLERANCE LIMITS.
Column "Action" decides the error or warning.
Regards
Shrikant.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.