STO Dates mismatch between ECC and APO

847 Views

Hello,

Could someone please let me know if there is any way of getting back the dates of an STO from ECC to APO whenever there is change in PDT in ECC.STO is created from APO is picking the transportation duration from APO and gets cif'ed to ECC.We have an enhancement in place to pick the same Planned delivery time upon being interfaced to ECC, so the dates match at that time.

However business expects that if there is any change made to planned delivery time of the STO in ECC then the dates should get reflected accordingly in APO.This is not happening,APO gets the delivery date from ECC but reschedules it according to the transportation duration in APO.This is not caught in CIF as well.

I tried changing the Publication settings to -Always transfer also tried the option of "No Rescheduling of Stock Transport Orders"i.e. i have set the indicator in CIFPUCUST02, ideally this should ensure that APO should adopt the dates from ECC instead of rescheduling it in APO wrt to transportation duration.

Please let me know if there is something i am missing