Completion date is not updating with TECO date in IP10

524 Views

Dear Experts,

I have created a maintenance plan with frequency is 5 Years. After scheduling system generated maintenance order, and I have completed the order with system date, Example. 25.06.2019.

As I did, in IP10 for the plan it is not showing completed date, and scheduling type/status " New start Called" for this work order

But, i chek in work order Tab Planning in Completion Date is not update/blank

im check SPRO is no problem,

How can I get update the Last completion date is as TECO date.