on 08-09-2019 9:17 PM
Hello,
I have 1 MRPc or manufacturing dept. which makes a part for 3 manufacturing depts. I have 3 Production versions set up (A001, A002, A003), but i'm having trouble getting the production orders to create based on which dept needs parts. (For example: 049, 012, and 031 all use the parts. if 049 has 5 pcs on hand but a requirement of 50, it should create a planned order for 45 pcs on A002 which is set with 049 as the Receiv. Location. but it is always selecting A001.)
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.