Is there any constraint when we give infoprovider as source to Delta Initialization BPC package in Organize Delta Initialization option?

I have one DSO with both Amount and Quantity as 2 separate key figures in same DSO and i have created 2 separate TRFN files. When i try to create Delta Initialization job for 2nd key figure, it gives an error "

Selection overlaps with delta initialization

is it the case that i cannot have more than one delta initialization load from same source DSO with multiple key figures and need to separate out amount and quantity in separate DSOs.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 13, 2017 at 06:12 AM

    But you can load both keyfigures simultaneously using MVAL in transformation file...

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 16, 2017 at 04:09 AM

    Thank You Vadim!