BW Experts,

I have 4 info packages which load deltas and are part of a process chain in production. When I put this process chain to production, I took a strategy not to transport the dev class associated with it so that any changes to be done in production must come thr' dev via transports. With no corresponding dev class being transported to production with this process chain, it will not allow to change the rescheduling of the proicess chain to some other time.

All of a sudden the BASIS Informed me that there is a 4 hr outage window today. but my process chain is schedule to run at that outage window. So I need to reschedule these process chains. As I said before this is not possible.

So this is the strategy i am adopting for a interim solution for today......

I am copying the info packages which load deltas in production and saving it as new info packages.

I am building a new process chain in production to include these new Info packages and schedule this process chain at a different time.

In my job monitor, sm37, i am going to cancel the original process chain which is scheduled to run during the outage window.

Questions:

If the new delta info packages are copied from the originals, are the delta affected?

Can i actually cancel a scheduled process chain in sm37?

Inputs will be appreciated....

Thanks

Ashwin

PS: The outage window is at 1:00pm EST...Have to do this before that:-)

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Mar 24, 2006 at 03:29 PM

    Yes I can find my process trigger job in SM37, and it is scheduled, but what is the exact way to cancel this scheduled job ?

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Thank you all for your inputs, This is what I am goin to do, AS i will be scheduling a brand new process chain with a different time, I will go ahead and just delete this existing this job. I guess that solves my problem.... Thanks you all once again.

      Cheers

      Ashwin

  • author's profile photo Former Member
    Former Member
    Posted on Mar 24, 2006 at 02:59 PM

    > Questions:

    >

    > If the new delta info packages are copied from the

    > originals, are the delta affected?

    <b>If the InfoPackages are exactly same, you should have no problem.</b>

    >

    > Can i actually cancel a scheduled process chain in

    > sm37?

    <b>

    In SM37 cancel a job that starts with BI-PROCESS-TRIGGER or something similar. Cancel that. Search by your ID or search by wild char process or smth.

    >

    ></b>

    > PS: The outage window is at 1:00pm EST...Have to do

    > this before that:-)

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.