After ATP check Follow-Up Material wasn't effctive

44 Views Last edit Jul 30, 2019 at 04:31 AM 2 rev

Hi,

I want to know that how the Effective-Out Date might be considered during the ATP check in production order?

I set material B as the Follow-Up Material of material A, and Effective-Out Date is 2019-07-01. Material A didn‘t have any stock.

And I added A into a production order which had creation date was 2019-06-25, requirements date was 2019-07-16.

After executing the ATP check, the Requirement Quantity didn't transfer from A to B. Meanwhile showed the missing part of A.

But if I also added A into a production order which had creation date after 2019-07-01 and executed the ATP check, the Requirement Quantity transferred successfully.

Does it mean that the Effective-Out Date comparing with order creation date but not requirement date in production order?