production order not doing backflush for components without batch assigned

The production order has 2 components with batch assigned in the component view and 2 other components without batch but with blackflush indicator assigned,

I have production confirmation coming from MES, when doing confirmation for one production order, the components consumed with mvt type 261 are only the 2 components that has batch assigned, and the ones with backflush indicator are not being consumed and does not appear in COGI.

Any idea why this is happening?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Feb 13, 2017 at 04:32 PM

    Any clue anyone?

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 14, 2017 at 11:50 PM

    run MM03 and check those two components - look at tab MRP2 - there should be 'Backflush' field NOT blank.

    anyway compare components (open 2 sessions with MM03) - one which was backflushed and another which was not.

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 15, 2017 at 06:35 AM

    Hi

    Please check T-Code CO1P.