The production order has 2 components with batch assigned in the component view and 2 other components without batch but with blackflush indicator assigned,

I have production confirmation coming from MES, when doing confirmation for one production order, the components consumed with mvt type 261 are only the 2 components that has batch assigned, and the ones with backflush indicator are not being consumed and does not appear in COGI.

Any idea why this is happening?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Alejandro Peña Cantu Feb 13, 2017 at 04:32 PM
0

Any clue anyone?

Share
10 |10000 characters needed characters left characters exceeded
SP RO Feb 14, 2017 at 11:50 PM
0

run MM03 and check those two components - look at tab MRP2 - there should be 'Backflush' field NOT blank.

anyway compare components (open 2 sessions with MM03) - one which was backflushed and another which was not.

Share
10 |10000 characters needed characters left characters exceeded
P Puri Feb 15, 2017 at 06:35 AM
0

Hi

Please check T-Code CO1P.

Share