on 07-16-2019 8:37 AM
Good Day all
I am trying to investigate the WO planned by the PM planner. I believe that the person does not reserve the required parts for the WO and thus puts the task onto the technicians to reserve the spares for themselves.
Is there a type of report that I can run to see who booked the spares, maybe according to a functional location, to have an idea of what is going on? else I would need to physically go through the WO and check the action log, which is extremely tedious.
So ideally the info I would need are WO, spares and who reserved the spares
Any ideas?
Hi
Yes, MB25 is more for reservations that are made directly on a cost centre, not that run over a word order. And it doesn't show the info that I require.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Did you check the report MB25?
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.