BYD Specialists,
Is it possible to change the cost center in a cost collecting project, after costs have been posted?
Adding a new task and changing the responsible unit, only allows the profit center change. Can we do the same for the cost center? If not, what do you recommend as a workaround?
Regards,
Sebastian
Hi Sebastian,
no, you cannot change the responsible cost center in any project after the project was released.
You need to close the one project and create a new one.
Here is an improvement request regarding this topic, that you may want to vote for.
Best regards
Otfried