Dunning Wizard - Level Issues

233 Views Last edit Jul 03, 2019 at 01:10 PM 2 rev

SAP B1 9.2 SQL

Dunning Levels seems to be set appropriately:

Dunning Letter 01 - 1 days

Dunning Letter 02 - 1 days

Dunning Letter 03 - 1 days

Dunning Terms are one letter per Dunning Level.

So when i run the Dunning Wizard it shows me that every BP is on level 1, even if interest days are 5+ days. I created new BP, and created environment that we have 3 invoices:

  • one invoice with overdue day 1 (it should be dunning level one so its correct)
  • one invoice with overdue days 2 (it should be dunning level 2 but sap show that it is dunning level 1)
  • one invoice with overdue days 5 (it should be dunning level 3 but sap shows that it is dunning level 1)

Sap always show dunning level 1, thats our problem.