Hi Expert,
My client want to rolled up the Maintenance order cost assigned to Network in WBS but it is not happening.
In PM order Project Network is assigned in Subnetwork Field. Order Cost is reflection on Standard SAP Cost Report but showing as separate line and Cost is not rolled up to the WBS level.
Here Project whose Network is assigned on Subnetwork Field of PM order is Statistical Project.
I have done the config setting in OPSV also and maintained line for Order category "20" Order type "PS20" which is order type of Project. Selected Indicator "Appended plan update" but didn't get sucess.
I also tried by selecting indicator "Assign fund in Plan" but then also PM Order cost didn't rolled up to WBS level.
Please suggest , if i missed any config to achieve this scenario
In OPSV make sure the PM order category is Appended and Apportioned.
And the PM order has to be account assigned to the WBS in both assignment locations. There are 2 places in a PM order where the WBS can be assigned, to be safe assign the WBS in both.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.