on 07-02-2019 12:35 PM
Hi Guys,
I would need to make a custom calculation of Date Finish Scheduling based of specific request of my customer.
This vaue is modificable automatically on CO02 -> functions -> schedule -> order with standard calc.
You now if is possible to abbly Custom Formula in User-Exits or Badis?
Alternately, do you think it is possible and appropriate to change this value using standard function module?
Regards,
D.
Hello,
What is the requirement to change the schedule finished date of production order?
Or you may check BAdi WORKORDER_UPDATEmethod INITIALIZE – Initialization when Importing/Creating Order
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Scheduled start and finished dates are determined by routing operation times and this process is SAP standard. I would suggest working with basic dates to align with customer requirements.
You can check the following forum to get the customer exists and BADI information.
https://wiki.scn.sap.com/wiki/display/ERPMan/User+exists+and+BADIs+of+production+order
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.