Hello All,

I have faced problem in SAP. I have done activity dependent planning, while KSII calculation system divides those cost equally which are not part of activity dependent planning. Hence i wanted to know is cost splitting required for activity dependent planning or how can i calculate in actual rate correctly.

Thanks,

Snehashis Paul

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi,

Splitting not required for dependent planning.

If you have already done the dependent planning....run KSPI for - Price Calculation

Thanks