on 06-25-2019 11:33 AM
Hello All,
I have faced problem in SAP. I have done activity dependent planning, while KSII calculation system divides those cost equally which are not part of activity dependent planning. Hence i wanted to know is cost splitting required for activity dependent planning or how can i calculate in actual rate correctly.
Thanks,
Snehashis Paul
Hi,
Splitting not required for dependent planning.
If you have already done the dependent planning....run KSPI for - Price Calculation
Thanks