Dear Experts,
I have a routing for which i have 14 operations and for each operation the time is 20 mins. Ideally the total cycle time should be 20*14 = 280 mins. But when I do a schedule test for the routing I see for each operation the schedule time is around 2min 30sec extra.So instead of 280 mins i am getting a cycle time of 319 mins. I am not able to understand from where the extra mins are coming. I do not have any floats maintained.The screenshots are attached. Thanks in advance.operation-detail.png