Hi experts!

Can anyone help with the following situation I am facing:

We have both demand and sales in plant, as well as manufacturing and storage. There is no transportation lane, therefore there is no Transportation Lead Time.

However, there is quality lead time to be considered, and it cannot be within the Production Lead Time.

We decided to configure a DC for the plant, so we can have a lane to set the quality lead time.

The question is: how do we copy the demand data to that new DC, since the demand - which is at the plant - will be copied from Supply Planning solution?

PS. Plant and DC are going to have different IDs, but they are physically at the same location.

I'd appreciate your help!

Thanks in advance.

Joao Vitor