Hello Gurus,

We have an issue with PM notification .

We have added Revision Level in Notification by activating LOG_EAM_POM & LOG_EAM_POM_2,

Now, When we try to create a notification from Order Screen and assign revision level in the notification and try to save, SAP gives a DUPM .

Please help

Regards

Rabindra

Accepted Solutions (0)

Answers (3)

Answers (3)

p244500
Active Contributor
0 Kudos

Can you provide rest of the dump infomation ?

former_member629424
Discoverer
0 Kudos

Thank you fro your quick response , We have already implemented the Note , but still the Error is appearing

Regards

Rabindra

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Rabindra

Please observe that this not a note to be simply implemented. This note suggests you to implement the report ZPM_QMNUM_I0071 , which is available in SAP note 492742, in order to fix an inconsistency that may cause this short dump.

Can you please confirm if you have already executed this report? Did you find any inconsistency?

If you have already implemented and ran the report, then you need to provide more information about the short dump. Usually, for a deeper analysis of the short dump we need to have the complete dump, which includes the piece of code where the dump happened and the call stack. So please go to ST22, open this dump, save it as a text file and the attach it to this question.

Regards,

Caetano