Hi guys we provide stock for subcontract 5 Pc and received 3 pc s remaining 2 pc are spoiled (collapse) in sc vendor so what is the next scenario

Accepted Solutions (1)

Accepted Solutions (1)

Mahendran8888
Contributor
0 Kudos

Hi,

Receive the product to the plant and do the quality test, move the quantity to Quality storage location or Dump it using 551 movement.

Regards

Mahendran P

0 Kudos

But here company not bare the amount of return goods so again they asked to sc vendor can do scrap how can we do it scenario?

Answers (1)

Answers (1)

ankurch
Active Contributor
0 Kudos

Hi There,

We did subsequent adjustment in this scenario!

Thanks,

0 Kudos

if it's quantity available under consumption or over consumption we can use but it was spoiled at subcontractor preemies suppose i given 5 shirts for stitching but i received 3 finally remains damaged .

ankurch
Active Contributor
0 Kudos

So, if you wanted to debit the cost to vendor you need to receive total quantity & post a credit memo for the same amount to the vendor.