Hi,
According to PLM315, the Estimate Costs Column of Costs tab, Costs subtab is editable.
But in my system ECC6.0 EHP8, the column is gray, the estimated costs cannot be input for each Value Category.
Could you please advise where I can set to change the column to be editable?
Thank you.
Ban
The issue is solved by creating estimated costs version from
SPRO-->Plant Maintenance and Customer Service-->Maintenance and Service Processing-->Basic Settings-->Settings for Display of Costs-->Define Version for Cost Estimates for Orders