For maintenance order capacity utilization always 100%

0 Kudos

Hi ,

my idea was to block a work center through PM for some hours or days so I see it on the planning board.

It works, but in the work center the capacity utilization is on 90%

That means, that the blocking time is more than my input in field "Normal duration of the activity".

I cant change the capacity utilization, so I have to have it for PM order everytime on 100%

Does someone have an idea how to solve it ? Preferably without coding.

Thankful for every idea and answer.

KR Marvin

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

After some search I found out that I can set three versions in workcenter with different capacity utilization. In PM order I can choose then this version that have 100% capacity utilization.

When you want to set 90% as basis, you should set in work center this version as active version.

KR Marvin