on 05-21-2019 12:46 PM
Hi ,
my idea was to block a work center through PM for some hours or days so I see it on the planning board.
It works, but in the work center the capacity utilization is on 90%
That means, that the blocking time is more than my input in field "Normal duration of the activity".
I cant change the capacity utilization, so I have to have it for PM order everytime on 100%
Does someone have an idea how to solve it ? Preferably without coding.
Thankful for every idea and answer.
KR Marvin
After some search I found out that I can set three versions in workcenter with different capacity utilization. In PM order I can choose then this version that have 100% capacity utilization.
When you want to set 90% as basis, you should set in work center this version as active version.
KR Marvin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.