Hi Experts,

How to update the planned annual values of WBS using CJR2, not monthly wise values.

Currently I have created layout and profile, after posting data using CJR2, the monthly values are getting updated in the report and not the annual values.

I dont want to update monthly values, i would like to see only annual values in the report, system should not distribute the annual values to monthly wise values.

Thanks and Regards,

Udaykumar P.P.

Accepted Solutions (0)

Answers (1)

Answers (1)

kenmelching
Active Contributor

All plan values in SAP are stored in the tables by fiscal period, this cannot be changed. You can view yearly values through reporting.

former_member345626
Participant
0 Kudos

Thanks for your revert Ken.

See, when I update cost plan through CJ40 for year 2019, the values are updated in period 000.2019 - Remainder 2019.

When I update through CJr2, the annual value is split into 12 periods. see the attached image of report S_ALR__87013533

Is there any way for CJR2 where in values will be updated similar to CJ40?budget-report-s-alr-87013533.jpg

In the attached image, 200 is updated using CJ40 and 100 amount is updated through CJR2 and system split it into 8.33 for 12 periods.

Thanks and Regards,

Udaykumar P.P.