Hello Experts,

We are using flexible planning SOP, issue which we are coming here is

As some of the materials still demand does not transferred during active version to demand management despite of having correct master data. Following are the issues persist during active version to demand transfer in GEP :

  1. Some of the materials demand got transferred Partially (Seems like it transferred based on PG proportion and distribution value)
  2. Some of the materials demand does not transferred even though they are having value in loaded as well as SCM forecast

We have set up foreacast delete to load new forecast using background jobs and which we are executing by using transactions MC8e and MC8G. Forecast uploaded via custom transaction but issue which we are facing as demand does not exist of some of the materials in MDPB table. As master data level below are criteria so all materials meeting below criteria but still issue is persist for few materials so appreciate on your expert advise.

  1. Be a member of a Product Group
  2. Product Group is part of the Planning Hierarchy
  3. Planning Hierarchy is fully maintained
  4. Have a planning strategy associated with it

Thanks,

Mayur

Accepted Solutions (0)

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Reset the regeneration time stamp for the planning programs using program RMCSCORS by selecting all option and then release the demand again.

Or you may try online transfer using transactions MC90, MC74 and MC75 for these affected materials.

Best Regards,

R.Brahmankar

0 Kudos

Hello Rupesh,

Thank you for responding to my query.I just would like to know root cause why demand in flexible SOP could not transfer to demand management despite of materials maintained correctly. How does programme RMCSCORS will help to solve this problem if i select all options ? I do not understand here, release demand after generation of this program,shall i need to release demand via MC75 or MC90 separately ?

We have found this issue during every month forecast load so do you mean we need to run this programe every time ? or Shall i set up background job which will transfer demand from active version to demand management ?

Appreciate your response.

Thanks,

Ravindra.

0 Kudos

Hello Rupesh,

I have executed RMCSCORS but nothing is happened in system as only got message as time stamp reset. When i check MDPB or MD63 demand does not exist for few materials. Please help me to further.

Thanks,

Ravindra.

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

After reset time stamp did you release the demand again?

Check the STATUS For job RMCP6RES

Then refresh Planning hierarchy RMCAXXX6

SOP TRANSFER DM RMCP6BIN

Best Regards,

R.Brahmankar

0 Kudos

Hello,

I do not understand release demand ? Do you mean i have to execute MC90 or MC74 to release demand ?

Thanks,

Ravindra

rupesh_brahmankar3
Active Contributor

Hello,

Re transferred demand to active version again and check the outcome.

Best Regards,

R.Brahmankar

0 Kudos

Hello Expert,

I will be appreciate on your expert advise here on this issue.

Thanks,

Ravindra.