May 20, 2019 at 01:35 PM

Block Planning with Alternate Modes in PPDS

299 Views

I have a scenario to use Alternate modes along with Block Planning.

To achieve this i have used the Same Class for Resource Classification for All resources and assigned Char values at Resource Level and also at resource selection condition at Recipe level . If the Char matches it creates alternative modes. Also i have included the Char Values for Blocks and assigned in the Resource selection condition.

Now as a result , i get correctly Alternate Modes in PDS as required. But in valuation, for the PDS, i also see two Block Char values.In APO, i have defined and assigned the same Class as Block class in Resource and in the char values, i have Only included values which are relevant for Block Planning.

Now after planning run the Planned orders are not getting assigned to existing blocks. Planend orders are created at the end of the period where the Blocks end.These orders alos cannot be manually dragged Inside the Blocks.

Please let me know how to setup so that i can use Block planning and Change of Mode uisng Alternate Mode and not using PV (Change source of Supply). All resources will have same Blocks and i expect orders to be moved from One Block of Reource to Similar Block of Another resource using drag & drop functionality.