Hello experts - This question is related to the S4HANA on cloud data migration activity, as in public tenant environment we have only Q & P and we cant refresh them and so what options are there to complete my data migration testing cycles in line with the test strategy? Can any experts respond please?
Hello Vani,
As you stated we only have 2 clients (Q/P) and there are currently no options for data refresh. I would approach the data migration testing strategy in a different way.
- Start with unit testing
- Load smaller data set loads (sampling - say 10% data or data used in test cases) in Q system
- Repeat sampling again for next test cycle in Q system
- Load complete data in P system after sign-off in Q system
Hope this helps.
Best,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Enda - Thanks for the reply, much appreciated, but still i am unable to reach to my question the answer. there are lot things given in the link which you have provided but unable to find the answer.
Can you please advise.
Regards
Vani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vani ,
Have you checked the Activate Roadmap ( https://go.support.sap.com/roadmapviewer/ ) or Best Practice Explorer ( https://go.support.sap.com/roadmapviewer/ ) for active scope items for Migration ?
Maybe the link https://go.support.sap.com/roadmapviewer/#/group//roadmap/SUITEONPREMAGL/node/901B0E6D3F501ED7B5C500... will be of use
Regards
Enda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.