Dear All,

I have a workflow program to change equipment maintenance and planning plant when creating shipping document.

If shipping document date is 01.04.2019 then equipment valid from date also change accordingly (01.04.2019).

But when i want to change valid from date from 01.04.2019 to 30.03.2019 system not change valid from date.

Kindly provide solution, how can i change valid from date.

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Kudos

Hi,

You cannot change the validity dates once created. Maybe you could use classification to store this shipping information..

I would suggest you tag this post with the following to get a better response: PLM Enterprise Asset Management (EAM)/Plant Maintenance (PM)

PeteA

Answers (1)

Answers (1)

shiva_08021
Explorer
0 Kudos

Hello Peter Sir,

Thanks for your valuable time to answer me.