05-14-2019 6:01 PM - edited 02-04-2024 2:34 AM
As planning in SAC using the live data connection is currently unavailable, what is the recommended practise for utilising actual data from the live connection as a base for creating plan data? I have a live connection setup from S/4 HANA Cloud 1902 to SAC.
To date I have had to create a planning model directly in SAC and import the actuals into SAC from an excel sheet (downloaded from S/4). Is there any other way of achieving this without the manual creation of master data in SAC and data upload via spreadsheet?
Hi Shane ,
may S/4 HANA Import data connection be useful to get actuals from S/4 instead downloading data to excel ! It may require configuration as described in https://help.sap.com/doc/00f68c2e08b941f081002fd3691d86a7/release/en-US/63140f17362947fe8bcd9c6960db...
Regards
Sateesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You could also enabled the S/4 CDS View as an 'Analytics enabled query' - this would create a transient infoprovider and SAC could consume it using it's BW Import connection.
Kind regards
H
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.