on 05-02-2019 2:11 PM
Hi Guru's
as my clients requirement he need that purchase order should not be create on monday . plz give solution . thanks
E mail - <email address removed by moderator>
Hi,
Please check planning calendar functionality fulfill your requirement.
https://blogs.sap.com/2013/10/20/planning-calendar/
https://blogs.sap.com/2014/10/09/how-planning-calendar-works/
If we use the planning calendar, the procurement proposals will be created according to the periods defined in the planning calendar which we have shown below Planning calendar is use at the material level and assign this in MRP2 view along with lot size procedure PK (period lot size according to planning calendar)
Ex: If the period start date will be Wednesday in the planning calendar with weekly calculation rule then during MRP run the system will group all the requirement which falls under the one week and MRP will create the single proposal on Wednesday for an entire week.
Another option is to control via enhancement or BADI implementation with the help of technical team.
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.