Hello,

Planned orders are generated from IBP order series optimizer. When we are viewing the orders in S4 MD04 it shows Start and end time as a single day and timestamp as 00:00:00.

Can we change it to start as 00:00:00 and end as 23.59.59 on same date/day

Thanks,

AKhilesh

Accepted Solutions (1)

Accepted Solutions (1)

Irmi_Kuntze
Advisor
Advisor
0 Kudos

you have a BADI available on ECC side that modifies the data coming from /IBP/ORDER_EXT table and before it writes to the several order types, meaning the BAdI is considered NOT with the integration, but with the job that creates the planned orders and deletes the entries in

/IBP/ORDER_EXT. Make sure you think about time zones before you do the coding (local or UTC).

If I remember correct, that was

/IBP/ECC_IF_EX_MODIFY_PREQ~MODIFY_PREQ_BEFORE_IN

Irmi

former_member367912
Participant
0 Kudos

Thanks for sharing the details Irmhild. Will try that and share my observation here.