I created a project code in SAP PS with one WBS but witthout a network. Can I use that WBS to raise PR/POs ?
BR
Indika
You can create manual PR/PO( ME21n/ME51N) and assign it to the WBS element ( System Status of WBS must be released), before that make sure you check user status which might be holding you to do that activity using transaction control and check the budget tolerance limits as well. Based on available budget you are allowed to post PR/PO/any actual.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can manually create PRs and POs using account assignment Q or P depending on the project valuation setting.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If the WBS is in released status, yes, you should be able to create purchase orders, depending on how availability control is set up
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.