Hello, how can I see the costing method (i.e. % of completion) used in projects (module PS), at profit center level or at company level? Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • May 05 at 02:28 PM

    Are you asking about using Progress Analysis in PS and then aggregating all of the projects by Profit Center or Company Code.

    Each project can have it's % progress calculated through Progress Analysis but there isn't a standard way of aggregating these values higher than the individual project.

    Add comment
    10|10000 characters needed characters exceeded

    • Thanks Ken for the answer. Where and how can I see, at individual project level then, the % of progress at a certain point in time, and the measurement rule, i.e. hours employed, costs incurred to date, etc. Sincerely.

  • May 06 at 11:15 AM

    You can see the settings in configuration under Progress Analysis. When you run Progress Analysis it will aggregate up the weighted POC values.

    Add comment