New release strategy re-triggering for old purchase orders (which was released against old release strategy) in below case:
Ex:
Initially i have created release strategy (R1) with below combination:
Plant: 1000 Doc.Type: NB, Value : 1 -1,00,000
And generated 10 PO's and released processed all the transactions,
Now business want to control the PO for 50,000 value limit,
because i have created new release strategy (R2) with same combination with new value limit & Locked Old release strategy (R1)
Plant: 1000 Doc.Type: NB, Value : 1 - 50,000
For New POs working fine.
For Old PO's if user changed any type of text also system removing old R.strategy R1 (because locked) & re triggering new release strategy R2 for old pos as well.
Now how can i control 1 release strategy need to control for specific period, if new strategy will create its only applicable for new po's.
Date control Class level is available but strategy level not available.
Please advise...