network costing is summarised in CN41N report

Dear Gurus,

I have done network costing for projects. I wanted to exectue CN41N report, but in the report the cost is displayed only at the WBS and network header level. I wanted to see the costs in activity and each component level. Kindly help me to get it.

Regards

Pandian

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    May 05 at 04:11 PM

    In config for Network Parameters make sure you have Activity Account Assignment checked.

    Add comment
    10|10000 characters needed characters exceeded

  • May 05 at 02:21 PM

    Please post a screen shot of the details. Check OPSV and make sure for Network category both Append and Assign are checked.

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Ken,

      Thanks for the reply. my OPSV settings are correct as per your comment. I have attached the screenshot of the issue. All my costs are total up at the network header level but I want to see at the each level like activity and component level.

      issue-pic-cn41n.jpg (399.3 kB)