Dear Gurus,

I have done network costing for projects. I wanted to exectue CN41N report, but in the report the cost is displayed only at the WBS and network header level. I wanted to see the costs in activity and each component level. Kindly help me to get it.

Regards

Pandian

Kehkashan
Participant
0 Kudos

Please Goto to CJ20n ,Choose activity, EDIT>COST>Calculate Cost

Save the Project

Then Check in CN41n

Accepted Solutions (1)

Accepted Solutions (1)

kenmelching
Active Contributor
0 Kudos

In config for Network Parameters make sure you have Activity Account Assignment checked.

Answers (1)

Answers (1)

kenmelching
Active Contributor
0 Kudos

Please post a screen shot of the details. Check OPSV and make sure for Network category both Append and Assign are checked.

0 Kudos

Hi Ken,

Thanks for the reply. my OPSV settings are correct as per your comment. I have attached the screenshot of the issue. All my costs are total up at the network header level but I want to see at the each level like activity and component level.