cancel
Showing results for 
Search instead for 
Did you mean: 

Collective PR at Activity level in Network

former_member210673
Participant

Hi,

As in subject line, I am trying to check option for Collective PR at 'Activity level' in Network. In OPUV, the Collective PR (Checkbox) option is generating a Single PR for ALL the activities assigned to Network.

We would like to have a Single PR for each Activity in Network. Please let me know if someone had done this before or any suggestions.

-thanks

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member210673
Participant
0 Kudos

@Ritesh,

I have assigned the Matl. components to activities Via Std. Network BOM which generated Reservation as Item category is 'L' at BOM Component level.

requirement is that User to be able to generate Single PR for certain set of Materials (I am also checking MRP Group - WBS Grouping WBS Element concept) which is not working and hence checking if atleast CNMM will work in this scenario where components are derived from Network BOM, so that End-user will select the components and 'Generate Pur Req'..

-Thanks

former_member210673
Participant
0 Kudos

Dear Ritesh,

Thanks for the suggestion. I have checked CNMM and getting below error. I will have to test the process and will then update. I am getting the below error when I select 'Line items' (Select All) and click on 'Execute - Group to Purchase Requisition'

Select a valid entry that is not relevant for requirements

Message no. CNMM006

-Thanks

ritzm
Explorer
0 Kudos

Hi,

Collective PR can be made at the network header only.

However, I would suggest you to try using transaction code "CNMM" (project oriented procurement). In this transaction code, try to select only the required material components under one activity and then click on the flag to create a purchase requisition for the selected components.

Please try this and share if it works.

Regards

Ritesh

0 Kudos

I don't think you will be able to do that. PR is against Network order.

Pramod