We have a server that has several reports scheduled in CMC. We have a new server and would like to move the scheduled reports over to our new server. We have done the Promotion Manger to move all the reports over to new server but need the scheduled settings moved. Any idea how to do this?

Accepted Solutions (1)

Accepted Solutions (1)

denis_konovalov
Active Contributor
0 Kudos

Promotion management is the right tool to do this. It will move your schedules etc..

Joe_Peters
Active Contributor

True, but you have explicitly select them in Dependencies.

Answers (1)

Answers (1)

former_member275473
Participant
0 Kudos

Thank you both for your replies. We did use Promotion Management and was able to get the schedules moved over.