All components are not getting assigned to project network activities.

Feb 10, 2017 at 10:43 AM

73

avatar image

Hello Experts,

I want to use CN33 functionality to assign material to project structure.

I have created Material BOM having 3-4 levels. I have put reference point also in all the components in BOM till last level. The same reference points are maintained in activities also. When I do CN33 transfer all material are not getting assigned to project only Header material and level next level materials are getting assigned.

What is the reason and what should I do to fix this?

10 |10000 characters needed characters left characters exceeded

For more clarifications Material BOM is created as below:

Header Material HEAD00010

Level 1 Material MFG00069, MFG00070

Level 2 Material PURCHASE00075, MFG00071, PURCHASE00077 (Components of MBTDIBL00069)

Level 2 Material PURCHASE00078, MFG00072 (Components of MBTDIBL00070)

Level 3 Material PURCHASE00076 (Components of MFG00071)

Level 3 Material PURCHASE00079 (Components ofMFG00072)

When I do CN33 only level 1 materials i.e. MFG00069, MFG00070 gets assigned to project structure activities and not other materials, Can someone explain me where I am going wrong?

Deepak
0
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Senthil Kumar Ganesan Feb 12, 2017 at 07:34 AM
0

Hi,

While transfering BOM ,check your selection parameters

1.Multi level

2.All items

Thanks,

Senthil Kumar Ganesan.

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Thanks Senthil

I did that but not all components are getting assigned to project network activity.

Deepak

0