Currently demand is restricted to 24 months, therefore production plans and inventory projections are not accurate when I run a 5yr plan.
How can missing customer demand be uploaded to SAP to allow for a scenario plan to be executed to show addtional production volumes and inventory projections (modules CM07 and MCBZ).
Thanks!
Hello,
In MS31 / MS32 you can set up the planning period up to next 5 years then save and release it.
However keep in mind it may impact the system performance. Do you really want to check the capacity and material requirement so far in future?
Best Regards,
R.Brahmankar