npv5.pngnpv3.pngnpv4.pngnpv2.png

Hi Team,

My requirement is to calculate NPV Automatically in PPM for Alerts.

I have done settings as per my understanding still, npv is not updating in PPM.
Could you please advise if I am missing any setting ? refer attached screenshots of the basic settings I configured.
I have run program to update financial planning which is updating Actual cost, plan cost and budget successfully but NPV is not updating.

/RPM/FICO_INT_PLANNING

Please advise at the earliest.

Regards

Gaurav

former_member225123
Participant
0 Kudos

Hi Guys,

Please share your expert advise.

Regards

Gaurav Ahuja

Accepted Solutions (0)

Answers (1)

Answers (1)

silvia_kreuzhuber
Active Participant
0 Kudos

Hi Gaurav,

your 2nd screenshot shows the switch 0007 / 0043 (Reference Interest Rate for Calculation of Net Present Value) defined as '14'. Can you please maintain the interest rate RPM_IRATE rather than the fin. view. Afterwards, retest the NPV calculation. In case it still fails then I suggest that you place a Customer Incident so that SAP Support can look into it.

Regards,