on 04-18-2019 4:26 PM
I have 6 plants using SAP PM on ECC6.0 (same instance). Preventive orders for 3 plants are always released with Basic finish date same as basic start date.
The other 3 plants do not have this issue. Maintenance Plans appear to be created in the same manner in all 6 plants. Any ideas on where to check for differences that could be causing this. Config for all 6 plants seems to be the same but I am obviously missing something.
Hi Steven.
You don't say whether these plans are strategy-based or not, but if they are, check the packages you used with IP11 and see if there are values maintained for the Lead Float and Follow-up Float. Those will affect the start and finish dates of the work orders.
Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Steve,
Please check transaction: OPU7 for Preventive order type in all maintenance plant.
Regards,
Ritesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.