I would be appreciated for your swift response. Check the following case below.

I am creating the production orders which is planned for 1000 Quantity of FG. And there will be 3 machine resources to produce the planned quantity. But during the production, one of the machine resource has been crashed and need to transfer the remaining work load to other machine. My question is how can I manage that kind of situation in ByD system. Production time to produce the 1000 quantity of FG will be impacted and how can I include that kind of information to production route report.

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Apr 15 at 02:53 PM

    Hi Khant Nyi Nyi Hein,

    Change the work center using CO02 with required work center, Routing also. If it is valid reason you can use change production order and discuss with your manager, get approval, discuss the cost impacted. Nothing will go wrong. Check the cost impact also. if your work center is not ready you can change the routing with consulting the team.

    Regards

    Mahe

    Add comment
    10|10000 characters needed characters exceeded